Business Analyst (BA) of the project to ensure all the below checklist tasks are performed and the status is updated before the Go/NoGo release call.

...

Tasks

Status

Status Date

Comments

Story for release are detailed, completed and closed (before code freeze)

Done 

 15th February 2024

 parent=rcf-31 and issuetype=story and fixVersion=RCF-0.9.0

Pending task/story is segregated (before code freeze)

Done

1st February 2024

Country reported bug has been listed and triaged

Done

1st February 2024

All tasks “fix version“ is in line with the release number (before code freeze)

Done

26th January 2024

Open bugs has been triaged (before code freeze)

Done

1st February 2024

parent=rcf-31 and fixVersion=RCF-0.9.0 and issuetype=bug and status not in (closed, canceled)

Known bugs are listed in release notes (before code freeze)

Done

20th February 2024

parent=rcf-31 and labels in (RCF_Known_Bug)

Test cases are reviewed (1 month before release)

Done

6th January 2024

UI workflow is reviewed as per the design (1 month before release)

Done

6th January 2024

UX is in compliance with MOSIP standard (before code freeze)

Done

22nd November 2023

https://xd.adobe.com/view/ea45ab2e-eb04-4643-8a57-5d0622a30705-bf16/

APIs are developed as per the requirement (before code freeze)

NA

NA

Posted the invite on community for external demo (a couple of days before the release)

Done

21st February 2024

https://community.mosip.io/t/the-android-registration-client-community-demonstration-version-0-9-0-release/1038

Legend

Anchor
Tasks
Tasks
Tasks:

  • The list of tasks against which the status needs to be updated. Since it’s a template, go ahead to add/modify as required

...