Date: 8-Jan-25
Attendees: Reeba Thomas , Pragya , Maheswara Sarma , madhu reddy , Sachin S P , Damodar Guru , HariKrishna Reddy , Khuddus shariff
What went Well | What went wrong | /goodWhat needs to be improved Comments | Improvement Plan | |
---|---|---|---|---|
Seamless collaboration between Dev & Dissemination team | Scope creep identified | All stakeholders should be part of daily standups | Design document to be prepared before any new feature addition | |
Team Spirit is HIGH | Dependencies between platform component teams | Dependencies should have been identified during the planning phase | New UI checklist including country data | |
Band width related issues | Work on Design document | |||
Handling Array of inputs were not happening | Scope is not clear | |||
Technical challenges during the build handover to QA team | ||||
0.11.0 release delay | TODO | |||
...