MVP Stage 1

(Not production ready)

MVP Stage 2

(Not production ready)

Production-ready with Minimal features

Platform Release

Objective : To become comfortable with code-base and build procedure

  1. Understand the design and code

  2. Build against 1.1.5.5/1.2 platform

  3. Min. necessary bug fixes

  4. Demo

Objective : MVP with new look-n-feel

  1. New look-n-feel using UI/UX design

  2. Flutter-based coding with approved UI/UX design

Objective : To get a production-ready platform with minimal features with new look-n-feel

  1. Basic feature parity with registration client

    1. QR-code scanning of the pre-reg ID

    2. Only new registration for adults and children

    3. Supervisor approval with EOD process

    4. Offline registration

    5. Preview and acknowledgement

    6. Multi-language support

    7. Server-side differentiation of the packet

    8. Development of SBI software on Bio-rugged tablet (Ethiopia team)

  2. Full testing and regression with mocks by the community (seek help from MOSIP QA team if required)

  3. Basic documentation

  4. Operator/Supervisor Manual

Note: The Ethiopia team should be able to consume it, customize it, test it and do a field rollout using their Bio-rugged tablets

Objective : Full functional release with feature parity with registration client

  1. Full feature-parity with registration client

    1. Settings page

    2. Lost UIN

    3. Update

    4. Biometric correction

    5. Center-remap

    6. others

  2. Complete documentation

  3. Full testing and regression by the community ((seek help from MOSIP QA team if required)

  4. Updated Operator/Supervisor manual

Note: The Ethiopia team should be able to consume it, customize it, test it and do a complete field rollout using their Bio-rugged and other tablets - SBI to be development by he vendors with facilitation by the country)