Date

Deployment Task

Day 1 to Day -3

3 days

  • Infra analysis

  • Deployment and configuration of MOSIP/Rancher Cluster

Day 4 and Day -5

2 days

  • Tech 5 ABIS Installation and configuration by the Tech5 team

  • MOSIP Services Installation and configuration

Day 6Health and Sanity Check with mock services

1 day

Complete health check

Day 7-8- Day 9-10

4 days

  • Configuration with Togo setup and configuration customizations

  • ABIS-MOSIP Configuration

  • Full Testing to check the stability of the On-Prem deployment by the MOSIP team

...

Resources : 2 DevOps engineer from MOSIP team who will do the deployment and 2 DevOps engineers from Togo team who would observe, take notes and learn.

...

Virtual Machines

The following is the table that depicts the Virtual Machine needs for carrying a successful MOSIP Deployment

...