On-Premise Deployment and Testing Plan

On-Premise Deployment and Testing Plan

Date

Deployment Task

Date

Deployment Task

Day 1-3

3 days

  • Infra analysis

  • Deployment and configuration of MOSIP/Rancher Cluster

Day 4-5

2 days

  • Tech 5 ABIS Installation and configuration by the Tech5 team

  • MOSIP Services Installation and configuration

Day 6

1 day

Complete health check

Day 7-8-9-10

4 days

  • Configuration with Togo customizations

  • ABIS-MOSIP Configuration

  • Full Testing to check the stability of the On-Prem deployment by the MOSIP team

Tentative start date - March 21, 2022 Tentative end date - April 1, 2022

Number of days required - 10 days approximately

Resources : 2 DevOps engineer from MOSIP team who will do the deployment and 2 DevOps engineers from Togo team who would observe, take notes and learn.


Virtual Machines

The following depicts the Virtual Machine needs for carrying a successful MOSIP Deployment

VM

CPU

RAM

DD

OS

svr-mosip-01

16

64

128

Ubuntu 20.04

svr-mosip-02

16

64

128

Ubuntu 20.04

svr-mosip-03

16

64

128

Ubuntu 20.04

svr-mosip-04

16

64

128

Ubuntu 20.04

svr-mosip-05

16

64

128

Ubuntu 20.04

svr-mosip-06

16

64

128

Ubuntu 20.04

srv-iam-01

8

16

64

Ubuntu 20.04

srv-abis-01

20

64

256

CentOS 7

srv-nginx-01

4

16

64

Ubuntu 20.04

srv-nginx-02

4

16

64

Ubuntu 20.04

srv-postgres

16

32

256

Ubuntu 20.04

srv-minIO

16

32

256

Ubuntu 20.04

srv-bastion

4

16

64

Ubuntu 20.04

 