ARC 0.10.0 Release Template

Page Title: ARC 0.10.0

Emoji :reminder_ribbon: Release Overview (Owner: PMO)

PMO

PO

QA SPOC

Dev SPOC

Team

,

Objective

  • Operator Onboarding

  • Update operator Onboarding

  • Dashboard

  • Hardening of DB

  • Transliteration (RTL)

  • 1.1.5 compatibility

Type of Release

Major

Status

Completed

Emoji :dart: Release Scope (Owner: PO)

In Scope

RCF: Scope Definition for 0.10.0 release - Android Registration Client - MOSIP (atlassian.net)

Out of Scope

  • Infant packet testing in 1.1.5

Dependencies

None

Emoji :triangular_flag_on_post: Milestones and deadlines (Owner: PMO)

Milestone

Owner

Deadline

Status

Comments

Release Planning Start Date

Feb 5, 2024

Completed

Date i just updated. Actual date will be updated based upon the QA team’s timelines

Sprint1 Start Date

Feb 12, 2024

Completed


Feature Freeze Date (usually Sprint n-1)

Feb 5, 2024

Completed


Code Freeze

Apr 25, 2024

Completed


QA Handover

May 30, 2024

Completed


Release Certification

Jun 7, 2024

Completed


Go\No Go Call

Jun 13, 2024

Completed


GA

Jun 14, 2024

Completed


Handover to Dissemination Team

Jun 28, 2024

Completed


Release Retrospective

Jun 14, 2024

Completed


Emoji :dart: Development plan (Owner: PMO)

  • Stakeholders: Architect\Dev Lead , Product Owner

  • Major attributes to consider are high-level estimates , team capacity and dependencies

Sprint Duration

RCF board - Agile board - MOSIP Issue Tracker (atlassian.net)

Number of sprints

7

Release Branch

Comments


Emoji :dart: QA plan (Owner: QA Manager)

  • Stakeholders: QA Spoc , Product Owner

QA Cycles planned

6 cycles

Verification Types

  • Manual Verification

  • Automation Testing

  • Documentation Review

Not in scope

eg: Upgrade testing, Real device testing

Emoji :dart: Security Testing Plan (Owner: PMO)

  • Stakeholders: Security Spoc , DevSecOps Manager

In Scope

Out of Scope for this release 0.10.0

Dates

N/A

Emoji :dart: Performance Testing Plan (Owner: PMO)

  • Stakeholders: Performance Testing Spoc , Performance Testing Manager

In Scope

Out of Scope for this release 0.10.0

Dates

N/A

Emoji :thinking: Risks\Challenges (Owner : PMO )

Risks

  • Transliteration in French cannot be verified. Library issues with icu4j

Challenges

API test reports from QA environment is taking time AI on QA team and Dev team: to fix issues

Emoji :calendar_spiral: Timeline (Owner: PMO)