ARC 0.10.0 QA Pre-release Checklist
Lead tester of the project to ensure all the below checklist tasks are performed and the status is updated before the Go/NoGo release call.
Owner : @N Chandra Sekhar ! @Maheswara Sarma
Tasks | Status | Completed Date | Comments |
---|---|---|---|
All the identified functional test cases have been executed and passing (before code freeze) | Go | 06/06/2024 |
|
Bugs for release are tested and closed (before code freeze) | Go | 04/06/2024 |
|
All the identified functional test cases have been reviewed by BA (before code freeze) | Go |
|
|
Country reported bug has been listed and tested | NA |
|
|
Environment of testing is with the right base, documented, verified and then testing is started (before start of testing) | Go | 06/06/2024 |
|
Complete one round of sanity testing with default config present in the mosip-config release branch | Go |
|
|
Release version testing against docker, artifacts, branch, env, etc. is documented and included in the test report (before code freeze) | Go | 06/06/2024 | Release branch 0.9.x |
Backward compatibility is tested (before code freeze) | NA |
|
|
Open bugs has been triaged along with BA (before code freeze) | Go |
|
|
Various aspects test coverage is factored: (1 month before code release)
| Go w.r.t Responsiveness | 06/06/2024 | Browser compatibility -NA Tested with mock SBI on
|
Executed Security Testing approach and outcome is reviewed (before code freeze) | NA |
|
|
Test automation is covering sufficient features via API, UI & DSL (before release) | Go | 06/06/2024 | UI |
Performance Testing approach, scripts, results and documentation is reviewed (before code freeze) | NA |
|
|
All testing artifacts are available in branch (before release) | Go |
|
|
Deployment testing is performed (before release) | NA |
|
|
Deployment documentation is reviewed (before release) | NA |
|
|
Upgrade testing is performed (before code freeze) | NA |
|
|
Upgrade documentation is reviewed (before release) | NA |
|
|
Functional documentation is reviewed (before release) | NA |
|
|
Detailed test report is available (before release) | Go |
|
|
Backward compatibility testing is performed (before code freeze) | NA |
|
|
iOS App Store publish ready (before release) (before release) | NA |
|
|
Android Play Store publish ready (before release) | NA |
|
|
Version compatability matrix updated as below | NA |
|
|
Version Compatibility Matrix
Module/Repo | Compatible Version | POM Version | Comments |
---|---|---|---|
| 1.2.0.1 |
| 1.2.0.1 B3 Version. All modules specs will be updated |
|
|
|
|
Legend
The list of tasks against which the status needs to be updated. Since it’s a template, go ahead to add/modify as required
Go - Go ahead from the stake holder to release for a given stream
NoGo - Stake holder does not want the release to go for a given stream
In-progress - Work is in progress to provide final decision for a given stream
NA - Specific part of section is not applicable for this release for a given stream
Enter the date when the Status was provided for a given stream
Enter the comments as relevant for a given stream