Lead documentation writer of the project to ensure all the below checklist tasks are performed and the status is updated before the Go/NoGo release call.
Owner: @vibha gondkar
Configuration Guide | Done | 10th June 2024 |
|
Overview of the feature | Done | 10th June 2024 |
|
README.md | Done | 10th June 2024 |
|
UI Spec Document | Done | 12th June 2024 |
|
Technology Stack Document | Done | 12th June 2024 |
|
User Guide | Done | 12th June 2024 | |
Test Report | Done | 10th June 2024 | |
Build and Deployment | NA | NA | |
KT Videos | Pending | ||
Developer’s Guide | Done | 10th June 2024 | |
Sonar Report | NA | NA | |
Release notes prepared | Done | 10th June 2024 |
Legend
Tasks:
The list of tasks against which the status needs to be updated. Since it’s a template, go ahead to add/modify as required
Status:
Go - Go ahead from the stake holder to release for a given stream
NoGo - Stake holder does not want the release to go for a given stream
In-progress - Work is in progress to provide final decision for a given stream
NA - Specific part of section is not applicable for this release for a given stream
Status Date:
Enter the date when the Status was provided for a given stream
Comments:
Enter the comments as relevant for a given stream