Country Pilot Go live - Plan

Key Milestones

Goal

Target Date

Status

Completion %

Notes

Goal

Target Date

Status

Completion %

Notes

  • Fix super critical high priority issues

  • Preparedness for operator/supervisor training

  • Onboard operators and devices onto Togo cloud

Mar 25, 2022

In Progress

 

 

  • Stabilize the Togo cloud

  • Complete on-prem deployment and configuration

  • Start/complete operator/supervisor training

Apr 1, 2022

Not Started

 

 

  • Stabilization of the on-prem environment

  • Biometric threshold exercise

  • End to End pre-pilot demo to the Togo team

Apr 8, 2022

Not Started

 

 

  • Pre-pilot readiness check and sanity testing

  • Preparation to go live

Apr 15, 2022

Not Started

 

 

 

Detailed Plan

Togo-Pilot Go-Live Detail Plan - Google Docs

Risks and Mitigations

Anticipated Risk

Owner

Mitigation Plan

Risk Status

Anticipated Risk

Owner

Mitigation Plan

Risk Status

Inaccessibility of SMS API

TOGO

TBD

 

Unstable internet connectivity on-prem environment may slow down process.

TOGO

TBD